June 1, 2026 The Mindshift from “Projects” to “Production” in FTTH
Part of Our Series of Top 10 Fiber Build Trends in 2026 and How to Manage for Them.
Telecom providers and others directing fiber-to-the-home (FTTH) builds have traditionally looked at those builds in a tactical, project-based way. The build for a given region would typically be assigned to the regional head of engineering or construction, who would break that overall build into manageable bite-size chunks to assign out to contractors. Their first question to the contractors they contacted was (and we know this because we heard it plenty) “how many crews do you have available and how soon can they start?”
Greater demands require a new approach
But build projects have gotten larger and the timing more aggressive. As a result, this old way of looking at builds in parts, rather than as a whole, is falling short. Why? Because it does not allow for the holistic perspective required to maximize coordination and efficiency. Given the industry-wide shortage of skilled labor available to do this work – a topic we will explore in a future article – boosting efficiency is an absolute imperative.
We’ve even seen this happen within a local build where job sites were divvied up among multiple contractors without considering how they needed to be activated. As a result, no contractor could be held accountable for activation nor work in a way to expedite it.
For more evidence, just look at the numbers. We routinely see programs where one market delivers near $1,200 per passing while another, using a similar construction model, exceeds $1,800. In some cases, deployment cycle times vary by 2X to 3X between regions despite comparable network designs.
Operational inconsistency is the cause:
- Design standards drift between markets
- Contractor performance varies widely
- Permitting workflows are not systematized
- Field conditions aren’t fed back into planning fast enough
Our boots-on-the-ground viewpoint is that the generals calling the shots – i.e., executives at the telecom companies driving these projects, could achieve better faster builds by stepping back from the traditional piecemeal approach to look at the overall build objective. Stated another way, we think the industry needs to shift from a project model to a large-scale production model. This would entail looking at the entire deployment system — design, permitting, construction, inspection and activation — to be able to operate with consistency across multiple work areas or regions simultaneously.
What fiber build operators should aim for
- Run centralized program control: A good PMO will have real-time visibility into cost, productivity and schedule across all markets.
- Standardize down to the component level: That shift typically includes centralized program management beyond the network design level. For example, deeper standardization within field construction practices such as routing rules, vault spacing, drop configurations and restoration procedures.
- Perform measurements: Milestones remain important, but the strongest operators manage around throughput metrics: footage installed per crew per day, drops completed per technician, permits cleared per week and inspection turnaround times.
The shift may appear subtle from the outside. But from an operational standpoint, the shift in thinking of FTTH deployment as a project business to a production business changes almost everything.
About ByVerTek, LLC
As fiber build experts, ByVerTek delivers turnkey services for digital infrastructure projects where failure is not an option. We leverage process and technology to meet demanding deadlines and quality standards across our service areas – design engineering, project management and construction for both FTTH and OSP (both aerial and underground) installation. As a result, ByVerTek has earned the trust of leading MSOs, telcos, overbuilders and others to build, upgrade and maintain their high-speed digital infrastructure. Learn more at ByVerTek.com